Comprehensive School Infrastructure Development Scheme (CSIDS)

(Button) Back to RD Schemes Back to Schemes

Related pages
  1. Scheme was launched during 2011-12 with an objective to provide basic infrastructure facilities in Panchayat union primary and middle school in rural areas.

  2. Providing new buildings, Kitchen sheds, Water Supply and Toilets.
  3. Repairs and Renovation of  existing facilities.
  4. New School building with RCC Roof with weathering course depending on the strength of students.
  5. New Kitchen sheds will be constructed additional rooms and store rooms may also be constructed.
  6. New Water Supply connection from panchayat or new borewell.
  7. Existing Water Supply will be taken up for repairs.

- In the year 2011-12 447 works have been taken up at an estimate cost of Rs. 405.490 lakhs. 

- In the year 2012-13 507 works have been taken up at an estimate cost of Rs. 447.210 lakhs. 

- In the year 2013-14 534 works have been taken up at an estimate cost of Rs.484.05 lakhs. 

     - In the year 2014-15 610 works have been taken up at an estimate cost of Rs.704.98 lakhs.

CSIDS 2014-2015 ABSTRACT

District : Tiruvallur

 

Date :   22.09.2014

Sl.
No.

Name of the
Block

Physical

Financial

No. of works
taken-up

No. of works
completed

Balance

% of Achievements

Allocation

Expenditure

Balance

% of Expenditure

1

2

3

4

5

6

7

8

9

10

Tiruvallur Division

1

Tiruvallur

42

25

17

59

27.725

15.414

12.311

55.60

2

Poondi

68

62

6

91

86.550

68.085

18.465

78.67

3

Kadambathur

24

23

1

95

35.035

30.659

4.376

87.51

Sub Total

134

110

24

82

149.310

114.158

35.152

76.46

Tiruttani Division

4

Tiruvalangadu

57

40

17

70

108.765

42.490

66.275

39.07

5

Tiruttani

47

29

18

61

43.880

17.044

26.836

38.84

6

Pallipat

32

32

0

100

46.025

46.025

0.000

100.00

7

R.K. Pet

72

46

26

63

90.588

40.248

50.340

44.43

Sub Total

208

147

61

70

289.258

145.807

143.451

50.41

Saidapet Division

8

Villivakkam

13

9

4

69

37.300

10.500

26.800

28.15

9

Puzhal

0

0

0

 

0.000

0.000

0.000

 

10

Sholavaram

25

18

7

72

28.410

13.380

15.030

47.10

11

Poonamallee

29

25

4

86

18.500

14.385

4.115

77.76

Sub Total

67

52

15

77

84.210

38.265

45.945

45.44

Ponneri Division

12

Minjur

85

59

26

69

111.252

48.406

62.846

43.51

13

Gummidipoondi

78

70

8

89

42.784

35.871

6.913

83.84

14

Ellapuram

38

26

12

68

28.168

14.628

13.540

51.93

Sub Total

201

155

46

77

182.203

98.904

83.299

54.28

Grand Total

610

464

146

76

704.981

397.134

307.847

56.333

 

CSIDS 2014 - 2015

Componentwise Physical and  Financial Progress - Abstract

Sl.
No.

Component

Physical

Financial         
                                      (Rupees in Lakhs)

Taken up

Completed

Pending

% of Completion

Allocation

Expenditure

Balance

% of Expenditure

1

New School Building

5

0

5

0

50.00

0.00

50.00

0.00

2

Compound Wall

50

28

22

56

158.80

70.15

88.65

44.18

3

Water Supply

23

23

0

100

45.45

45.45

0.00

100.00

4

Repairs to School Building

297

183

114

61

362.01

194.07

167.94

53.61

5

Repairs to Kitchen Shed

75

70

5

93

22.53

21.34

1.20

94.70

6

Repairs to School Toilet

160

160

0

100

66.20

66.13

0.06

99.90

Total

610

464

146

76

704.98

397.13

307.85

56.33